Check List For Montage

Check list for Installation

Check List for Installation

This check list is a guide and SkanDek A/S cannot be held responsible for potential deficiencies.

Click here for the PDF version of this checklist.

  1. Please contact our Production Technical Department for the loading schedule MINIMUM 3 working days before installation. Click here to send a mail to PTD, and a loading schedule will be prepared – OK ?
  2. Check and measure the building. Remember to do cross measurements-OK?
  3. Mark module of the elements on the abutment before instalment –OK?
  4. Ensure that stringers/steel beams are correctly placed for attachment of the SkanDek panels –OK?
  5. Lay the first panel – spend extra time to make sure this panel is correctly placed –OK?
  6. Ensure that the abutment is minimum 100 mm thick –OK?
  7. Fasten the panel with single shot nails at each end –OK?
  8. Use a spacer to achieve the correct distance between the panels. There should be 16 mm between the joints –OK?
  9. Continue point 6-8 until you come up against a wall.
  10. Ensure that the panels are properly fastened to the stabilising walls –OK?
  11. Fasten the SkanDek panels according to the instructions in the Installation Folder – OK?
  12. At the longitudinal joints, you must make sure that the bethyl band adheres properly so the vapour barrier is tight between the panels –OK?
  13. At the end of a panel, and where the panels come up against a wall, you must make sure that the vapour barrier overlap is fastened correctly according to SkanDek’s Installation Folder –OK?
  14. Reinsulate at the longitudinal joints and mount the lock plates according to the instructions in the Installation Folder –OK?
  15. Install compression-proof [isolation (20 mm or 50 mm) in the longitudinal joints according to the instructions – OK?
  16. Install compression-proof isolation (20 mm or 50 mm) in the longitudinal joints according to instructions – OK?
  17. Brand bottom cover in the longitudinal joints or shred the foil –OK?
  18. Complete and isolate the end panels, and fit 3 metres long L brackets for abutment of the trapezoid plate –OK?
  19. Lay insulation and create modfalskiler from murkrone. Then secure bottom cover by burning or weld on roof foil.
    For sheet roofs, both bottom- and top layer sheets are required
    For foil roofs (Protan), one layer of roof foil is enough; however extra foil is needed ved modfalskiler/perforations etc.

It is important to point out that a roof must NEVER be left before it is shredded. Roofs should ALWAYS be tight and closed when the workday is over.

When laying the roof in rainy conditions, the longitudinal joints should be shredded before laying the panels.

Skudpistoler.

Der findes mange egnede skudpistoler på markedet til svær montage. De mest udbredte skudsøm og pistoler til fastgørelse af SkanDek-elementer er fra hhv. Hilti og Spit.

Hilti DX 76.

Afløser for DX 750. Passer til bl.a. X-ENP-19 L-15 skudsøm. Enkelt- skudspistol. Sømmet indføres i mundingen og fastholdes af magnet. Patronmagasinet (strips m. krudtladning) føres ind i patronkammeret på siden.

Hilti DX 76.

Afløser for DX 750. Passer til bl.a. X-ENP-19 L-15 skudsøm. Enkelt- skudspistol. Sømmet indføres i mundingen og fastholdes af magnet. Patronmagasinet (strips m. krudtladning) føres ind i patronkammeret på siden.

Spit RH 525L.

Passer til skudsøm af typen Spit PPS HSBR14. Enkeltskudspistol. Kan benyttes opretstående og med magasinslange- studs. Relativt svagt rekyl.